Skip to main content

Steps to Supervising your Storey Building Project to Save Cost/Materials/Time

TRENCH EXCAVATIONS
PAD FOUNDATION




REINFORCEMENT AND PLUMBING
CASTING
BLOCK WORK AND FACIAL

APPROACH VIEW



When you have decided to invest your hard earn money in a building project or to supervise a building contract, one of the major worry that will envelopes your mind is how to go about it -save cost of materials, cost of labour, and the total site management of  time and resources. It is important to try minimizing loss to contractors/workers/labourers from stage of site clearance, foundation, wall erection to finishes.
From this write up, i will discuss and guide you on how to supervise a storey building, assuming a fairly stable soil that can allow for a pad foundation,
(see Pad foundation : http://constructionindustrysecrets.blogspot.com/2015/02/foundation-type.html)  and acquit with the stages of storey building project.
Below is the guide list, enjoy as you follow.

Case study: A Two (2) storey building (A ground floor and a top or suspended floor)
                                                               

S/N

CONSTRUCTION STAGES

MATERIAL REQUIRED
1.
Get A genuine Plot Of Land
Money (i.e. Naira/Dollars)
2.
Do/get the Survey Plan For the Plot.
( From a Registered Surveyor)

Money (i.e. Naira/Dollars)
3.
Do/get the Building/Architectural Plan.
(From an Architect/Builder/Civil Engr/Draft Men)

Money (i.e. Naira/Dollars)
4.
Structural –Reinforcement Design and Detailing.
(From a Civil/Structural Engineer)

Money  (i.e. Naira/Dollars)
5.
Clearing of Site.
(By Labourers)

Cutlass, Money etc
6.
Setting Out
(By Competent Builder/Architect/Engineer)
Profiles, Wooden Pegs, Baton, Nails, Rope, Square etc. Money
7.
Digging-Trench/Foundation Excavation.
(By Labourers  & Competent  Supervisor)

Digger, Shovel, Money
8.
Casting/Blinding of Foundation + Pad Footing, Column Reinforcement Erecting
(By Mason, Labourers   &  Competent  Supervisor)

Cement,Aggregates,Water,Mixer,Iron Rods/Reinforcements, Money
9
Foundation Block Works/Block Setting out
(By Mason, Labourers   &  Competent  Supervisor)

Blocks, cement, Block ,fine Aggregates, Water, Money
10.
Laterite Filling
(By Labourers   &  Competent  Supervisor)
Lateritic Materials, Boulders/Hard Cores, Stones, etc. Money
11.
Compaction/Ramming
(By Labourers  and Competent  Supervisor)

Rammer, Water, Money
12
Casting Oversite Concrete/German Floor/DPC, Plumbing (installation & erections of PVC Drain Pipes & Fittings)
(By Mason, Plumber, Labourers  & Competent ) Supervisor)
Hardcore, DPC Membrane/Nylon (optional),
Wood/Plank,PVC Pipes and fittings,
Fine And Coarse Aggregates, Water, Money
13
Block Wall on Concrete/ German Floor  To Window Base Level
(By Mason, Labourers   &  Competent  Supervisor)


Sharpsand,Block,Cement,Water
14
Block Wall from Window Base To Lintel Level
(By Mason, Labourers   &  Competent  Supervisor)

Blocks,Sharpsand,Cement,Water,Money
15
Lintel + Column erection & casting
(By Mason, Carpenter, Iron Bender, Labourers  and Competent  Supervisor)

Wood/plank, Iron Rods,Nails,Cement, Aggregates, Binding Wire, Water, Money
16
Block Wall  after Lintel
(By Mason, Labourers Competent  Supervisor)

Blocks,Sharpsand,Cement,Water,Money
17
Head Beam + First Floor Concrete Decking, Plumbing & Electrical installations.
(By Mason, Carpenter, Electricians, Iron Bender, Labourers  and Competent  Supervisor)
Wood/plank, plywood(optional), DPC Membrane/Nylon ,PVC Pipes and fittings, Electrical cables and box fittings, Rods,Nails,Cement,Aggregates,Iron Rod, Binding Wire, Water, Money
18
Block Wall On Deck Floor to Window Base Level
(By Mason, Labourers Competent  Supervisor)

Blocks,Sharpsand,Cement,Water,Money
19
Block Wall From Window Base to Lintel Level
(By Mason, Labourers   &  Competent  Supervisor)

Blocks,Sharpsand,Cement,Water,Money
20
Lintel+ Column erection & casting
R (By Mason, Carpenter, Iron Bender, Labourers  and Competent  Supervisor)
Wood/plank, Iron Rods,Nails,Cement,Aggregates,Iron Rod, Binding Wire, Water, Money
21
Block Wall  after Lintel
(By Mason, Labourers Competent  Supervisor)

Blocks,Sharpsand,Cement,Water,Money
                                
                          FOR MORE OR HIGHER STOREY OR FLOORS, REPEAT   STEP 17 – 21

22
Roof Beam + Concrete Facial/Parapet (Optional).
(By Mason, Carpenter, Iron Bender, Labourers  and Competent  Supervisor)
Wood/Plank, Plywood, Iron Rods,Nails,Cement, Aggregates, Binding Wire, Water, Money
23
Roof (Skeleton) + Ceiling nagging (Optional)
(By Carpenters and Competent  Supervisor)

Wood/Plank, Nails, Money
24
Roof covering
(By Carpenters and Competent  Supervisor)

Aluminium,stone coat Roofing Sheets, Money etc
25
Installations
(By Carpenter,plumber,Electricians, Labourers, etc.Competent  Supervisor)

Electrical cables,PVC pipes and fittings Pipes and Doors,windows,money etc.
26
Plaster of Paris (P.O.P)  (Optional)
(By P.O.P Specialist and Competent  Supervisor)

P.O.P Materials, Money
27
Finishes.
(By Mason, Carpenter, Painters, Tilers, Labourers, etc. Competent  Supervisor)
Plaster sand, Sharp sand, Cement, paints,Water,Money








Comments

Popular posts from this blog

Construction Procedure of Surface Road Side Drainage-PART 1 (with picture)

Surface water ( i.e., rain water) that falls on the ground surface such as; open field, paved areas or road surface, roof tops etc are channeled to a main drain naturally or through a constructed channel which is referred to as drainage. Procedure for construction of a common drainage (trench) (1m x 1m U drainage) (reinforced). includes; I.       Marking Of Alignment: The surveyor marked out the alignment for the trench to be dug. II.       Digging/Excavation: The surveyor marked out the dept of the trench to be excavated with a mechanical excavating machine. For a 1m x 1m drainage, the mathematical process of obtaining the required dept is to sum together the dept of the required drain + base + blinding. For dept:  A drain of dept1000 mm, base of 150 mm and blinding of 50 mm. Hence 1000mm + 150mm + 50mm = 1200mm (1.2 m) So an excavation of 1200mm (1.2m) is required from the to level of the road surface. For width:

Construction Procedure of Surface Road Side Drainage-PART 2 (with picture)

  V.        Next step is laying of concrete base on the blinded surface and the positioned reinforcement. A concrete base of 150 mm is to be laid or cast on the blinded floor, concrete grade C20 of ratio 1:2:4 is allowed (See concrete grading and mix ratio). A guiding panel is placed into position to guild in the laying of the concrete base in order to achieve a uniformly alignment base edge, thickness and width, also to manage concrete material while pouring. The base is cast with the U shape reinforcement bottom in between the concrete base achieving concrete cover below and above.   VI.        After setting and drying of the concrete base, next is to position the side wall panel form work. The floor base is marked to give the required one meter (1000 mm) internal width where the panel will be positioned. The panel wall spacing is 100mm, and wall height of 1000mm (1 meter), the panel is lubricated, clipped and prepared to accept the Concrete.

Setting out of a building

A building is set out in order to accurately define the outline and width of the excavation and to determine the center line of the proposed building walls, so that construction according to the building professionals drawing (the architectural plan) plan can be transfer into the ground, this building process is called setting out of building. The center line method of setting out is generally preferred and adopted Setting out can be a very complex engineering process but with need experience its quite easy. Experienced engineer and surveyors are those involved in setting out of structures, in large projects, services of land surveyors are required for more accurate transfer of levels and angles in setting out with the aid of a Theodolite to decided point around the building area But we are going to concern ourselves with the most common setting out method ·          Setting out using pegging ·          Setting out using blocks. But here, we will be discussing