Construction Procedure of Surface Road Side Drainage-PART 1 (with picture)

Surface water ( i.e., rain water) that falls on the ground surface such as; open field, paved areas or road surface, roof tops etc are channeled to a main drain naturally or through a constructed channel which is referred to as drainage.


Procedure for construction of a common drainage (trench) (1m x 1m U drainage) (reinforced). includes;


I.      Marking Of Alignment:


The surveyor marked out the alignment for the trench to be dug.



II.      Digging/Excavation:



The surveyor marked out the dept of the trench to be excavated with a mechanical excavating machine.
For a 1m x 1m drainage, the mathematical process of obtaining the required dept is to sum together the dept of the required drain + base + blinding.


For dept:

 A drain of dept1000 mm, base of 150 mm and blinding of 50 mm.
Hence 1000mm + 150mm + 50mm = 1200mm (1.2 m)

So an excavation of 1200mm (1.2m) is required from the to level of the road surface.


For width:

A minimum of (2.5 x width) m is advisable.
 For a 1 m x 1m drainage,
Since the drainage internal width is 1m, using
   1.5  x width =
2.5 x 1m = 2.5m
2.5m width excavation minimum is acceptable to create space for construction work area.



III.      The next step after excavation of drainage is the CONCRETE BLINDING.



Blinding is done on the surface area in order to correct any irregularities in level of the bed of the excavated surface, and to provide a smooth, level and regular surface to receive the concrete base. It’s usually ±50 mm depending on the rate of regularity of the surface area. Concrete Grading C10 or C15 as sub-soil might require.

see concrete grading,

the blinding is a mass concreting and its advisable to spread to cover entire width of the excavated trench except where there is need for material management.



 IV.      Reinforcement (iron Rod) positioning.





For a 1m x 1m drainage, a 12mm U shape reinforcement (spaced between 150mm to 300 mm or as designed) is placed into position on the blinded surface but positioned at the centre of the base with the aid of concrete biscuit to create a concrete cover.
There should be concrete cover between the reinforcement and the base of the drain concrete base and the top of the drain wall.
Hence, Reinforcement Rod height needed should be;

1000mm (reinforcement height) + 75mm (base top conc. Cover) - 25mm (wall top concrete cover) = 1035mm (1.035m) .

NB: the center of the reinforcement base should be align with the centre alignment provided by the surveyor in order to have consistently uniform alignment.



Comments

Popular posts from this blog

Construction Procedure of Surface Road Side Drainage-PART 2 (with picture)

  V.        Next step is laying of concrete base on the blinded surface and the positioned reinforcement. A concrete base of 150 mm is to be laid or cast on the blinded floor, concrete grade C20 of ratio 1:2:4 is allowed (See concrete grading and mix ratio). A guiding panel is placed into position to guild in the laying of the concrete base in order to achieve a uniformly alignment base edge, thickness and width, also to manage concrete material while pouring. The base is cast with the U shape reinforcement bottom in between the concrete base achieving concrete cover below and above.   VI.        After setting and drying of the concrete base, next is to position the side wall panel form work. The floor base is marked to give the required one meter (1000 mm) internal width where the panel will be positioned. The panel wall spacing is 100mm, and wall height of 1000mm (1 meter), the pan...

Setting out of a building

A building is set out in order to accurately define the outline and width of the excavation and to determine the center line of the proposed building walls, so that construction according to the building professionals drawing (the architectural plan) plan can be transfer into the ground, this building process is called setting out of building. The center line method of setting out is generally preferred and adopted Setting out can be a very complex engineering process but with need experience its quite easy. Experienced engineer and surveyors are those involved in setting out of structures, in large projects, services of land surveyors are required for more accurate transfer of levels and angles in setting out with the aid of a Theodolite to decided point around the building area But we are going to concern ourselves with the most common setting out method ·          Setting out using pegging ·      ...