Skip to main content

BENEFITS OF CHOOSING STONE COATED ROOFING SHEET

DURABLITY :
Stone coated roofing sheet are very durable and has about 50years company guarantee.


ABSORBS RADIATION:
Stone coated tiles has ability of absorbing the ultraviolet sun rays.

ABSORBES HEAT:
Stone coated roofing sheet has great ability of absorbing heat, and this reduces the amount of heat that enters the building via the roofing,most other roofing sheet cant reduce heat.

FULLY FIRE RESISTANT :
Coated roofing sheet is fully resistant to fire, heat, water and harsh weather condition. It’s truly the best


VERY ATTRACTIVE:
When you see a building coated with stone coated tile, you would know that there is a difference.

AESTHETIC VALUE :
Its a piece of Architectural beauty



Comments

Popular posts from this blog

Setting out of a building

A building is set out in order to accurately define the outline and width of the excavation and to determine the center line of the proposed building walls, so that construction according to the building professionals drawing (the architectural plan) plan can be transfer into the ground, this building process is called setting out of building. The center line method of setting out is generally preferred and adopted Setting out can be a very complex engineering process but with need experience its quite easy. Experienced engineer and surveyors are those involved in setting out of structures, in large projects, services of land surveyors are required for more accurate transfer of levels and angles in setting out with the aid of a Theodolite to decided point around the building area But we are going to concern ourselves with the most common setting out method ·          Setting out using pegging ·      ...

Construction Procedure of Surface Road Side Drainage-PART 1 (with picture)

Surface water ( i.e., rain water) that falls on the ground surface such as; open field, paved areas or road surface, roof tops etc are channeled to a main drain naturally or through a constructed channel which is referred to as drainage. Procedure for construction of a common drainage (trench) (1m x 1m U drainage) (reinforced). includes; I.       Marking Of Alignment: The surveyor marked out the alignment for the trench to be dug. II.       Digging/Excavation: The surveyor marked out the dept of the trench to be excavated with a mechanical excavating machine. For a 1m x 1m drainage, the mathematical process of obtaining the required dept is to sum together the dept of the required drain + base + blinding. For dept:  A drain of dept1000 mm, base of 150 mm and blinding of 50 mm. Hence 1000mm + 150mm + 50mm = 1200mm (1.2 m) So an excavation of 1200mm (1.2m) is required...

Ring / Pipe Culverts Construction procedure

Culvert is an open/close drain structure that allows water to flow below a road. It’s like a tunnel carrying a stream of water flow. A Ring/Pipe Culvert Procedure for construction of a common Ring/Pipe Culvert (road junction culvert) includes; I.       Marking Of Alignment: - The surveyor marked out the alignment for the trench to be dug. II.       Digging/Excavation: The surveyor marked out the dept of the culvert to be excavated with an excavating machine. For a 1m pipe culvert, the mathematical process of obtaining the required dept is to sum together the total width of the pipe + base + blinding. For dept:  A pipe of width 1000 mm, base of 150 mm and blinding of 50 mm (though optional). . Hence 1000mm + 150mm + 50mm = 1200mm (1.2 m) So an excavation of 1200mm (1.2m) is required from the to level of the natural ground (sub grade level) surface. For wid...