Skip to main content

Glass

Glass is one of the oldest and most versatile materials known to man through  ages. Glass occurs naturally as a volcanic ash 🌋 known as obsidian. Artificial glass was first made about 4000 years ago. The term glass is normally used to describe a particular state of matter, known as glassy or vitreous State, which is obtainable when a liquid cools without crystallization taking place, With solid properties characterized by its brittleness, hardness, transparency and chemical inertness.

Comments

Popular posts from this blog

Setting out of a building

A building is set out in order to accurately define the outline and width of the excavation and to determine the center line of the proposed building walls, so that construction according to the building professionals drawing (the architectural plan) plan can be transfer into the ground, this building process is called setting out of building. The center line method of setting out is generally preferred and adopted Setting out can be a very complex engineering process but with need experience its quite easy. Experienced engineer and surveyors are those involved in setting out of structures, in large projects, services of land surveyors are required for more accurate transfer of levels and angles in setting out with the aid of a Theodolite to decided point around the building area But we are going to concern ourselves with the most common setting out method ·          Setting out using pegging ·      ...

Construction Procedure of Surface Road Side Drainage-PART 1 (with picture)

Surface water ( i.e., rain water) that falls on the ground surface such as; open field, paved areas or road surface, roof tops etc are channeled to a main drain naturally or through a constructed channel which is referred to as drainage. Procedure for construction of a common drainage (trench) (1m x 1m U drainage) (reinforced). includes; I.       Marking Of Alignment: The surveyor marked out the alignment for the trench to be dug. II.       Digging/Excavation: The surveyor marked out the dept of the trench to be excavated with a mechanical excavating machine. For a 1m x 1m drainage, the mathematical process of obtaining the required dept is to sum together the dept of the required drain + base + blinding. For dept:  A drain of dept1000 mm, base of 150 mm and blinding of 50 mm. Hence 1000mm + 150mm + 50mm = 1200mm (1.2 m) So an excavation of 1200mm (1.2m) is required...

Ring / Pipe Culverts Construction procedure

Culvert is an open/close drain structure that allows water to flow below a road. It’s like a tunnel carrying a stream of water flow. A Ring/Pipe Culvert Procedure for construction of a common Ring/Pipe Culvert (road junction culvert) includes; I.       Marking Of Alignment: - The surveyor marked out the alignment for the trench to be dug. II.       Digging/Excavation: The surveyor marked out the dept of the culvert to be excavated with an excavating machine. For a 1m pipe culvert, the mathematical process of obtaining the required dept is to sum together the total width of the pipe + base + blinding. For dept:  A pipe of width 1000 mm, base of 150 mm and blinding of 50 mm (though optional). . Hence 1000mm + 150mm + 50mm = 1200mm (1.2 m) So an excavation of 1200mm (1.2m) is required from the to level of the natural ground (sub grade level) surface. For wid...