Skip to main content

Portland Cement production.

Production of Portland cement starts with two basic materials; a Calcareous material and an Argillaceous material.  The calcareous material is a calcium oxide, such as limestone, chalk, or oyster shells, the Argillaceous material is combination of alumina and silica obtainable from clay, shale, and blast furnace. the materials are passed through a grinding mill, using wet or dry process to the kiln.  In the kiln, the raw materials are melted at temperature of 1400 oC  to 1650 oC,  changing the raw materials into Cement clinker which is then cooled  and stored. The final process involved grinding the clinker into a fine powder, adding gypsum to regulate the setting time if the cement in the concrete.
The final product can be transported in stored bulk or sacks.

Comments

Popular posts from this blog

Construction Procedure of Surface Road Side Drainage-PART 1 (with picture)

Surface water ( i.e., rain water) that falls on the ground surface such as; open field, paved areas or road surface, roof tops etc are channeled to a main drain naturally or through a constructed channel which is referred to as drainage. Procedure for construction of a common drainage (trench) (1m x 1m U drainage) (reinforced). includes; I.       Marking Of Alignment: The surveyor marked out the alignment for the trench to be dug. II.       Digging/Excavation: The surveyor marked out the dept of the trench to be excavated with a mechanical excavating machine. For a 1m x 1m drainage, the mathematical process of obtaining the required dept is to sum together the dept of the required drain + base + blinding. For dept:  A drain of dept1000 mm, base of 150 mm and blinding of 50 mm. Hence 1000mm + 150mm + 50mm = 1200mm (1.2 m) So an excavation of 1200mm (1.2m) is required...

Construction Procedure of Surface Road Side Drainage-PART 2 (with picture)

  V.        Next step is laying of concrete base on the blinded surface and the positioned reinforcement. A concrete base of 150 mm is to be laid or cast on the blinded floor, concrete grade C20 of ratio 1:2:4 is allowed (See concrete grading and mix ratio). A guiding panel is placed into position to guild in the laying of the concrete base in order to achieve a uniformly alignment base edge, thickness and width, also to manage concrete material while pouring. The base is cast with the U shape reinforcement bottom in between the concrete base achieving concrete cover below and above.   VI.        After setting and drying of the concrete base, next is to position the side wall panel form work. The floor base is marked to give the required one meter (1000 mm) internal width where the panel will be positioned. The panel wall spacing is 100mm, and wall height of 1000mm (1 meter), the pan...

Setting out of a building

A building is set out in order to accurately define the outline and width of the excavation and to determine the center line of the proposed building walls, so that construction according to the building professionals drawing (the architectural plan) plan can be transfer into the ground, this building process is called setting out of building. The center line method of setting out is generally preferred and adopted Setting out can be a very complex engineering process but with need experience its quite easy. Experienced engineer and surveyors are those involved in setting out of structures, in large projects, services of land surveyors are required for more accurate transfer of levels and angles in setting out with the aid of a Theodolite to decided point around the building area But we are going to concern ourselves with the most common setting out method ·          Setting out using pegging ·      ...