Skip to main content

Ring / Pipe Culverts Construction procedure




Culvert is an open/close drain structure that allows water to flow below a road. It’s like a tunnel carrying a stream of water flow.


A Ring/Pipe Culvert

Procedure for construction of a common Ring/Pipe Culvert (road junction culvert) includes;

I.      Marking Of Alignment: -


The surveyor marked out the alignment for the trench to be dug.



II.      Digging/Excavation:



The surveyor marked out the dept of the culvert to be excavated with an excavating machine.

For a 1m pipe culvert, the mathematical process of obtaining the required dept is to sum together the total width of the pipe + base + blinding.


For dept:

 A pipe of width 1000 mm, base of 150 mm and blinding of 50 mm(though optional)..
Hence 1000mm + 150mm + 50mm = 1200mm (1.2 m)

So an excavation of 1200mm (1.2m) is required from the to level of the natural ground (sub grade level) surface.


For width:

A minimum of (2.5 x width) m is advisable.
 For a 1m pipe drainage,
Since the drainage internal width is 1m, using
1.5  x width =
2.5 x 1m = 2.5m
2.5m width excavation minimum is acceptable to create space for construction work area.



III.      The next step after excavation of drainage is the CONCRETE BLINDING and                          foundation base preparation.





Blinding  (though  optional) is done on the surface area in order to correct any irregularities in level of the bed of the excavated surface, and to provide a smooth, level and regular surface to receive the concrete base. It’s usually ±50 mm depending on the rate of regularity of the surface area. Concrete grading C15 is acceptable.
(See concrete grading and mix ratio). A concrete base of ±150 mm is to be laid or cast on the blinded floor, concrete grade C15 of ratio 1:2:4 is allowed (See concrete grading and mix ratio).
A guiding panel is placed into position to guild in the laying of the concrete base in order to achieve a uniformly alignment base edge, thickness and width, also to manage concrete material while pouring. The base is cast with the U shape reinforcement bottom in between the concrete base achieving concrete cover below and above.


 IV.      After setting, curing and drying of the concrete base, next is to arrange the pre-cast pipe           Culvert/Rings into the align position.







 V.       After arranging the pre-cast pipe Culvert/Rings into the align position, arranging the                 form work panel and then casting of concrete.

Taking the pipe/ring dimension to be 1000 mm (1.0m), the thickness of the concrete from the form work panel to the pre-cast ring/pipe is 200mm more or less on both sides depending on the design.

Hence the total width thickness of the drain would be;

i.e. 1000mm + 200mm + 200 mm = 1400mm (1.4m)


The total height of the drain would be;

Taking the pipe/ring dimension to be 1000 mm (1.0m), the thickness of the top slab concrete from the top of the pre-cast ring/pipe is between 200mm - 300mm more or less depending on the design.


Hence, the total height of the drain would be;

i.e. 1000mm + 300mm = 1300mm (1.4m)

Assuming the thickness of the top slab concrete from the top of the pre-cast ring/pipe is between 300mm,

Also, the reinforcement for the head wall is placed into position.

The concrete is then cast






Concrete cast.


After casting, and setting, the panel is removed and concrete cured.





Preparation of head wall panel in preparation to casting






VI   Back filling and compaction is then carried out in order to avoid future settlement.










Comments

Popular posts from this blog

Construction Procedure of Surface Road Side Drainage-PART 1 (with picture)

Surface water ( i.e., rain water) that falls on the ground surface such as; open field, paved areas or road surface, roof tops etc are channeled to a main drain naturally or through a constructed channel which is referred to as drainage. Procedure for construction of a common drainage (trench) (1m x 1m U drainage) (reinforced). includes; I.       Marking Of Alignment: The surveyor marked out the alignment for the trench to be dug. II.       Digging/Excavation: The surveyor marked out the dept of the trench to be excavated with a mechanical excavating machine. For a 1m x 1m drainage, the mathematical process of obtaining the required dept is to sum together the dept of the required drain + base + blinding. For dept:  A drain of dept1000 mm, base of 150 mm and blinding of 50 mm. Hence 1000mm + 150mm + 50mm = 1200mm (1.2 m) So an excavation of 1200mm (1.2m) is required from the to level of the road surface. For width:

Construction Procedure of Surface Road Side Drainage-PART 2 (with picture)

  V.        Next step is laying of concrete base on the blinded surface and the positioned reinforcement. A concrete base of 150 mm is to be laid or cast on the blinded floor, concrete grade C20 of ratio 1:2:4 is allowed (See concrete grading and mix ratio). A guiding panel is placed into position to guild in the laying of the concrete base in order to achieve a uniformly alignment base edge, thickness and width, also to manage concrete material while pouring. The base is cast with the U shape reinforcement bottom in between the concrete base achieving concrete cover below and above.   VI.        After setting and drying of the concrete base, next is to position the side wall panel form work. The floor base is marked to give the required one meter (1000 mm) internal width where the panel will be positioned. The panel wall spacing is 100mm, and wall height of 1000mm (1 meter), the panel is lubricated, clipped and prepared to accept the Concrete.